Your cart is currently empty!
PSM I – Practice Assessment 3
PSM I – Practice Assessment 3
Quiz-summary
0 of 80 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
Information
This is the third PSM I practice assessment with the following characteristics:
- Passing score: 85%
- Time limit: 60 minutes
- Number of questions: 80
- Format: Multiple Choice, Multiple Answer and True/False
- Difficulty: Intermediate
- Language: English only
You can navigate throughout the questions whenever you want. The unanswered questions are marked in the navigation bar. You can click on the “review question” button to flag it for later review.
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 80 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- Answered
- Review
-
Question 1 of 80
1. Question
Usually, there is a prescriptive approach in a methodology for selecting practices and tools but a framework is a boundary, which leaves room for other practices and tools.
Pick 1Correct
A methodology is a set of principles, tools, and practices, which can be used to guide processes to achieve a particular goal. Usually, there is a prescriptive approach in a methodology and tends to replace the creativity, autonomy and, thinking of people.
A framework is a boundary, which leaves room for other practices and tools to be included but provides much of the process required. Usually, a framework is an abstract process with a freedom of selecting and using other concrete processes and practices in it.
Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems. The Scrum framework is purposefully incomplete, only defining the parts required to implement Scrum theory. So, the Scrum Team on its own defines how it wants to create value through a variety of practices and tools.
Therefore, Scrum is a framework not a methodology, technique, tool, or practice.
Incorrect
A methodology is a set of principles, tools, and practices, which can be used to guide processes to achieve a particular goal. Usually, there is a prescriptive approach in a methodology and tends to replace the creativity, autonomy and, thinking of people.
A framework is a boundary, which leaves room for other practices and tools to be included but provides much of the process required. Usually, a framework is an abstract process with a freedom of selecting and using other concrete processes and practices in it.
Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems. The Scrum framework is purposefully incomplete, only defining the parts required to implement Scrum theory. So, the Scrum Team on its own defines how it wants to create value through a variety of practices and tools.
Therefore, Scrum is a framework not a methodology, technique, tool, or practice.
-
Question 2 of 80
2. Question
Scrum is a(n):
Pick 1Correct
Scrum is an implementation of the agile mindset and is based on an adaptive approach that fundamentally comes from empirical process control and lean thinking against the predictive or plan-driven approach that waterfall and other traditional methods are based on.
Incorrect
Scrum is an implementation of the agile mindset and is based on an adaptive approach that fundamentally comes from empirical process control and lean thinking against the predictive or plan-driven approach that waterfall and other traditional methods are based on.
-
Question 3 of 80
3. Question
The Scrum Team could work on two Product Goals simultaneously.
Pick 1Correct
Scrum Teams must fulfill (or abandon) one Product Goal before taking on the next one.
Incorrect
Scrum Teams must fulfill (or abandon) one Product Goal before taking on the next one.
-
Question 4 of 80
4. Question
What should a Scrum Master do when the Developers decide not to conduct Sprint Retrospective?
Pick 1Correct
Scrum Master does not have a position to instruct others. Scrum Master tools are teaching, coaching, mentoring, facilitating, helping, and guiding. In addition, a Scrum Master should focus on the Developers empowerment. So, it is not an acceptable policy to raise issues to top management immediately. Furthermore, the level of freedom depends on the maturity level of the Team. Even, the most mature Team does not have complete freedom because they should at least work within organizational boundaries. Finally, the main elements of Scrum are mandatory and immutable so the Team should not remove them because the result is not Scrum.
Incorrect
Scrum Master does not have a position to instruct others. Scrum Master tools are teaching, coaching, mentoring, facilitating, helping, and guiding. In addition, a Scrum Master should focus on the Developers empowerment. So, it is not an acceptable policy to raise issues to top management immediately. Furthermore, the level of freedom depends on the maturity level of the Team. Even, the most mature Team does not have complete freedom because they should at least work within organizational boundaries. Finally, the main elements of Scrum are mandatory and immutable so the Team should not remove them because the result is not Scrum.
-
Question 5 of 80
5. Question
What are the characteristics of a high-performance Scrum Team?
Pick all that applyCorrect
A high-performance Scrum Team lives the Scrum Values deeply. Mistakes are mandatory and when they are made, they are celebrated. There are many constructive conflicts based on trust in the Team. Instead of living by the rules, they make the rules. They help their customers become more successful. The Team can release the Increment with just one press of a button through an automated continuous delivery pipeline. They evolve DoD (Definition of Done) over time and add more stringent criteria to it continuously and adhere to it completely. Almost every Sprint, the Team reaches the Sprint Goal and sometimes they exceed expectations. You can obviously see a high level of creativity, productivity, and accountability in the Team. Members are highly knowledgeable, autonomous, and self-organizing and use continuous improvement in all aspects of their processes and environment.
Incorrect
A high-performance Scrum Team lives the Scrum Values deeply. Mistakes are mandatory and when they are made, they are celebrated. There are many constructive conflicts based on trust in the Team. Instead of living by the rules, they make the rules. They help their customers become more successful. The Team can release the Increment with just one press of a button through an automated continuous delivery pipeline. They evolve DoD (Definition of Done) over time and add more stringent criteria to it continuously and adhere to it completely. Almost every Sprint, the Team reaches the Sprint Goal and sometimes they exceed expectations. You can obviously see a high level of creativity, productivity, and accountability in the Team. Members are highly knowledgeable, autonomous, and self-organizing and use continuous improvement in all aspects of their processes and environment.
-
Question 6 of 80
6. Question
In a project, customers are not satisfied with the software pages’ load speed. The Product Owner knows that they are right. How can the Scrum Master help the Product Owner to cope with this issue?
Pick 2Correct
This issue is a type of non-functional requirement that can be managed by adding them to the Definition of Done, adding them to the Product Backlog, or adding them to the acceptance criteria. In addition, transparency is the fundamental thing that all Scrum Team members should try to increase. So, the Product Owner should have the courage to talk about the issue directly with the Developers. On the other hand, the Scrum Team uses empiricism approach so they always inspect and adapt their way of working. Therefore, if the Product Owner finds a concern should share it with the Developers as soon as possible in order to prevent further deviation. Consequently, although the Sprint Retrospective is a great time to talk about this issue, the Team should not wait until this event occurrence. Finally, the Scrum Master should not give the solution (i.e. ask DevOps group) because it harms the Team’s self-management.
Incorrect
This issue is a type of non-functional requirement that can be managed by adding them to the Definition of Done, adding them to the Product Backlog, or adding them to the acceptance criteria. In addition, transparency is the fundamental thing that all Scrum Team members should try to increase. So, the Product Owner should have the courage to talk about the issue directly with the Developers. On the other hand, the Scrum Team uses empiricism approach so they always inspect and adapt their way of working. Therefore, if the Product Owner finds a concern should share it with the Developers as soon as possible in order to prevent further deviation. Consequently, although the Sprint Retrospective is a great time to talk about this issue, the Team should not wait until this event occurrence. Finally, the Scrum Master should not give the solution (i.e. ask DevOps group) because it harms the Team’s self-management.
-
Question 7 of 80
7. Question
What are the duties of the Product Owner in a Scrum Team?
Pick 3Correct
During the Sprint, the Product Owner works with the Developers to clarify requirements and answer developers’ questions. (S)he manages Product Backlog through ordering, breaking down PBIs, creating new Items, and sometimes assigning value to the Items. Refines the Product Backlog continuously with the Developers’ collaboration. Participates actively in the Sprint Planning, Sprint Review, and Sprint Retrospective events. In addition, measures project performance, collaborates and engages with customers and stakeholders. Furthermore, developing and explicitly communicating the Product Goal is one of their important activities.
Incorrect
During the Sprint, the Product Owner works with the Developers to clarify requirements and answer developers’ questions. (S)he manages Product Backlog through ordering, breaking down PBIs, creating new Items, and sometimes assigning value to the Items. Refines the Product Backlog continuously with the Developers’ collaboration. Participates actively in the Sprint Planning, Sprint Review, and Sprint Retrospective events. In addition, measures project performance, collaborates and engages with customers and stakeholders. Furthermore, developing and explicitly communicating the Product Goal is one of their important activities.
-
Question 8 of 80
8. Question
Daily Scrum is a mandatory event of Scrum that should be conducted every day. Who should start the meeting every day?
Pick 1Correct
Daily Scrum is an event just for the Developers in which they check their progress towards the Sprint Goal and make a plan for the next 24 hours. Consequently, the Scrum Master and the Product Owner are not present in the meeting to start the Daily Scrum. In addition, using a token is just a technique and optional which is not a required rule to determine who should start the meeting. Finally, the Developers themselves decide on who should start the meeting.
Incorrect
Daily Scrum is an event just for the Developers in which they check their progress towards the Sprint Goal and make a plan for the next 24 hours. Consequently, the Scrum Master and the Product Owner are not present in the meeting to start the Daily Scrum. In addition, using a token is just a technique and optional which is not a required rule to determine who should start the meeting. Finally, the Developers themselves decide on who should start the meeting.
-
Question 9 of 80
9. Question
The Product Owner is accountable for maximizing the value of the product. So (s)he selects enough Product Backlog Items for the Sprint to maximize the value.
Pick 1Correct
The Product Owner or Scrum Master should not determine or force the Developers to select enough items from the Product Backlog because this manner decreases their commitment, as they may not believe they can finish all the selected items until the end of the Sprint. It is up to the Developers to select enough items for the Sprint without any worry about blame or outside force, as they know the best how to do the work. Therefore, the authority of selecting enough amount of PBIs for the Sprint belongs to the Developers.
Incorrect
The Product Owner or Scrum Master should not determine or force the Developers to select enough items from the Product Backlog because this manner decreases their commitment, as they may not believe they can finish all the selected items until the end of the Sprint. It is up to the Developers to select enough items for the Sprint without any worry about blame or outside force, as they know the best how to do the work. Therefore, the authority of selecting enough amount of PBIs for the Sprint belongs to the Developers.
-
Question 10 of 80
10. Question
What is a Product?
Pick all that applyCorrect
Based on the Scrum Guide 2020 definition, a product is a vehicle to deliver value. It has a clear boundary, known stakeholders, well-defined users or customers. A product could be a service, a physical product, or something more abstract.
Incorrect
Based on the Scrum Guide 2020 definition, a product is a vehicle to deliver value. It has a clear boundary, known stakeholders, well-defined users or customers. A product could be a service, a physical product, or something more abstract.
-
Question 11 of 80
11. Question
What are the duties of the Developers in a Scrum Team?
Pick 2Correct
The Developers have many responsibilities as following:
Developing and creating Increments, estimating the Product Backlog Items and tasks, creating the Sprint Backlog, selecting Items for the Sprint Backlog, decomposing selected Product Backlog Items into tasks, measuring Sprint performance and productivity, calculating velocity, resolving Team internal conflicts, collaborating in composing/refining the DoD, making technical decisions, etc.
On the other hand, assigning value to the Product Backlog is the Product Owner’s responsibility and removing impediments is the Scrum Master’s responsibility.
Incorrect
The Developers have many responsibilities as following:
Developing and creating Increments, estimating the Product Backlog Items and tasks, creating the Sprint Backlog, selecting Items for the Sprint Backlog, decomposing selected Product Backlog Items into tasks, measuring Sprint performance and productivity, calculating velocity, resolving Team internal conflicts, collaborating in composing/refining the DoD, making technical decisions, etc.
On the other hand, assigning value to the Product Backlog is the Product Owner’s responsibility and removing impediments is the Scrum Master’s responsibility.
-
Question 12 of 80
12. Question
In a project, the Developers should wait for the result work of a third-party to continue its work, otherwise, they will be idle. Therefore, they ask the Product Owner to re-order the Product Backlog in order to maximize their utilization. As a Scrum Master, what would you advise?
Pick 1Correct
The Product Owner’s main accountability is maximizing the flow of value delivery. His/her tool to meet this purpose is Product Backlog ordering. Maximizing people’s utilization is not a goal of Scrum. Instead, Scrum focuses on creating and delivering value. Maximizing Team utilization does not guarantee the Team creates maximum value. If the Developers are really idle, they can work on improving their working process, paying back technical debt, refactoring, improving their knowledge, …
Incorrect
The Product Owner’s main accountability is maximizing the flow of value delivery. His/her tool to meet this purpose is Product Backlog ordering. Maximizing people’s utilization is not a goal of Scrum. Instead, Scrum focuses on creating and delivering value. Maximizing Team utilization does not guarantee the Team creates maximum value. If the Developers are really idle, they can work on improving their working process, paying back technical debt, refactoring, improving their knowledge, …
-
Question 13 of 80
13. Question
Which one is a characteristic of the Developers?
Pick all that applyCorrect
The Developers have many characteristics as following:
Have no titles, preferably full-time, with no sub-teams, autonomous, self-organizing, self-managing, and cross-functional.
Incorrect
The Developers have many characteristics as following:
Have no titles, preferably full-time, with no sub-teams, autonomous, self-organizing, self-managing, and cross-functional.
-
Question 14 of 80
14. Question
Promoting self-management and cross-functionality is the Scrum Master’s responsibility.
Pick 1Correct
The Scrum Master has many responsibilities as following:
Establishing the Scrum framework, ensuring Scrum is understood by everyone, ensuring Scrum is enacted, helping others to find techniques, may facilitate the events if required or requested, facilitating the Team’s decision making, removing or causing the removal of impediments, working with other Scrum Masters, helping the organization to adopt Scrum, planning and advising Scrum implementations within the organization, teaching time-boxing to the Team members, ensuring the Product Owner spends enough time with the Developers and stakeholders, promoting self-organization, self-management, cross-functionality, etc.
Incorrect
The Scrum Master has many responsibilities as following:
Establishing the Scrum framework, ensuring Scrum is understood by everyone, ensuring Scrum is enacted, helping others to find techniques, may facilitate the events if required or requested, facilitating the Team’s decision making, removing or causing the removal of impediments, working with other Scrum Masters, helping the organization to adopt Scrum, planning and advising Scrum implementations within the organization, teaching time-boxing to the Team members, ensuring the Product Owner spends enough time with the Developers and stakeholders, promoting self-organization, self-management, cross-functionality, etc.
-
Question 15 of 80
15. Question
Which one is a characteristic of the Scrum Master?
Pick 3Correct
The Scrum Master has many characteristics as following:
One Scrum Master for each Team, servant leader, a manager (not managing people but managing Scrum process), not a project manager, not a team leader, full-time or part-time, can be the Product Owner or a member of the Developers at the same time, etc.
Incorrect
The Scrum Master has many characteristics as following:
One Scrum Master for each Team, servant leader, a manager (not managing people but managing Scrum process), not a project manager, not a team leader, full-time or part-time, can be the Product Owner or a member of the Developers at the same time, etc.
-
Question 16 of 80
16. Question
Which one in Scrum is accountable for the Product quality?
Pick 1Correct
The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint. In fact, creating quality products is a teamwork endeavor. So, the whole Scrum Team is accountable for the product quality.
Incorrect
The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint. In fact, creating quality products is a teamwork endeavor. So, the whole Scrum Team is accountable for the product quality.
-
Question 17 of 80
17. Question
The Sprint Backlog is a plan by and for the Developers.
Pick 1Correct
The Sprint Backlog is a plan by and for the Developers. It is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal.
Incorrect
The Sprint Backlog is a plan by and for the Developers. It is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal.
-
Question 18 of 80
18. Question
Who is responsible for adding or removing the Developers?
Pick 1Correct
The Scrum Team is self-managing so it could make decisions about adding or removing members. In fact, they are the start point of making decisions for adding or removing members. However, each organization has its own process for adding or removing the Team members that is triggered by the Scrum Team. In addition, sometimes removing a member could be converted into an impediment. In such a case, the Scrum Master can intervene to help the Team removing that person.
Incorrect
The Scrum Team is self-managing so it could make decisions about adding or removing members. In fact, they are the start point of making decisions for adding or removing members. However, each organization has its own process for adding or removing the Team members that is triggered by the Scrum Team. In addition, sometimes removing a member could be converted into an impediment. In such a case, the Scrum Master can intervene to help the Team removing that person.
-
Question 19 of 80
19. Question
Which traits are emerged when the Developers get self-managing?
Pick 3Correct
When a Team is self-managing, it can manage its work without any need for outside guides or orders. In addition, in the self-management state, creativity, productivity, flexibility, and commitment (buy-in) will emerge.
Incorrect
When a Team is self-managing, it can manage its work without any need for outside guides or orders. In addition, in the self-management state, creativity, productivity, flexibility, and commitment (buy-in) will emerge.
-
Question 20 of 80
20. Question
You are in the tenth Sprint and your stakeholders are really unhappy about the result of the product and disappointed about their investment. What do you think may cause this situation?
Pick 3Correct
The Sprint Review is a great place to inspect and adapt the progress of the project at the end of each Sprint. After ten Sprints, this just shows that both the Scrum Team and the stakeholders have not been using this event adequately. The stakeholders might not participate in the Sprint Reviews actively. The Product Owner might not inform the stakeholders continuously. Moreover, even they might not have gathered feedback from the market effectively. On the other hand, there is no project manager role in Scrum and indeed there are not any control mechanisms like project control, PMO (project management office), etc. in Scrum projects. Finally, the stakeholders should not push their ideas to the Scrum Team.
Incorrect
The Sprint Review is a great place to inspect and adapt the progress of the project at the end of each Sprint. After ten Sprints, this just shows that both the Scrum Team and the stakeholders have not been using this event adequately. The stakeholders might not participate in the Sprint Reviews actively. The Product Owner might not inform the stakeholders continuously. Moreover, even they might not have gathered feedback from the market effectively. On the other hand, there is no project manager role in Scrum and indeed there are not any control mechanisms like project control, PMO (project management office), etc. in Scrum projects. Finally, the stakeholders should not push their ideas to the Scrum Team.
-
Question 21 of 80
21. Question
What should the Developers do when one outside the Team orders them to do unplanned work?
Pick 1Correct
The Product Owner is accountable for maximizing the value of the Developers’ work. Changing the Sprint Backlog items in the middle of the Sprint may endanger the Sprint Goal and interrupt Team’s focus. So, in this case, the Developers should inform the Product Owner so that (s)he can work with the one who has ordered unplanned work.
Incorrect
The Product Owner is accountable for maximizing the value of the Developers’ work. Changing the Sprint Backlog items in the middle of the Sprint may endanger the Sprint Goal and interrupt Team’s focus. So, in this case, the Developers should inform the Product Owner so that (s)he can work with the one who has ordered unplanned work.
-
Question 22 of 80
22. Question
Creating a done and potentially releasable Increment is the purpose of each Sprint.
Pick 1Correct
The Team tries to produce a done usable and potentially shippable and releasable Increment and a piece of working software at the end of each Sprint. Sprints are the heartbeat of Scrum, where ideas are turned into value.
Incorrect
The Team tries to produce a done usable and potentially shippable and releasable Increment and a piece of working software at the end of each Sprint. Sprints are the heartbeat of Scrum, where ideas are turned into value.
-
Question 23 of 80
23. Question
How does the Product Owner order the Product Backlog?
Pick 1Correct
Although there are a lot of methods and guides for ordering Product Backlog such as importance, value, ROI, cost, new knowledge, risk, etc., the final say is the Product Owner’s opinion. Therefore, (s)he can order Product Backlog items based on whatever (s)he deems most important through his/her perspective.
Incorrect
Although there are a lot of methods and guides for ordering Product Backlog such as importance, value, ROI, cost, new knowledge, risk, etc., the final say is the Product Owner’s opinion. Therefore, (s)he can order Product Backlog items based on whatever (s)he deems most important through his/her perspective.
-
Question 24 of 80
24. Question
When a person switches between two or more teams, his/her productivity will increase.
Pick 1Correct
When a person works in two or more teams, (s)he will pay context-switching cost. It means (s)he should pay warm-up, preparation time, and resource for each switch. Therefore, (s)he will be less productive rather than when just works on one team.
Incorrect
When a person works in two or more teams, (s)he will pay context-switching cost. It means (s)he should pay warm-up, preparation time, and resource for each switch. Therefore, (s)he will be less productive rather than when just works on one team.
-
Question 25 of 80
25. Question
What will happen for the undone Sprint Backlog Items at the end of the Sprint?
Pick 1Correct
If the Team does not complete all Sprint Backlog Items at the end of the Sprint, the Sprint will be over with the completed Items. There is no blame or other same things. However, it is a valuable fact as an input for the Sprint Retrospective to inspect if there is any problem in the development process or anything else.
Extending or shortening a special Sprint duration is forbidden. Undone Items should not be included in the Increment. Instead, all undone Items should be re-estimated and move back to the Product Backlog and if through Product Backlog ordering, these Items remain on top of the Product Backlog, they can be selected for the next Sprint.
Incorrect
If the Team does not complete all Sprint Backlog Items at the end of the Sprint, the Sprint will be over with the completed Items. There is no blame or other same things. However, it is a valuable fact as an input for the Sprint Retrospective to inspect if there is any problem in the development process or anything else.
Extending or shortening a special Sprint duration is forbidden. Undone Items should not be included in the Increment. Instead, all undone Items should be re-estimated and move back to the Product Backlog and if through Product Backlog ordering, these Items remain on top of the Product Backlog, they can be selected for the next Sprint.
-
Question 26 of 80
26. Question
Which one is NOT a Sprint maximum time-box?
Pick 2Correct
The Sprint is used as a container for other events and its length can be explained as a maximum in various ways i.e. 30 days, one calendar month, a month or 4 weeks.
Incorrect
The Sprint is used as a container for other events and its length can be explained as a maximum in various ways i.e. 30 days, one calendar month, a month or 4 weeks.
-
Question 27 of 80
27. Question
You are the Scrum Master of a Scrum Team. The Developers for each release need to ask the DevOps team to prepare some prerequisites. However, the DevOps team usually does the preparation with delay. The Developers ask you for help. What would be your first reaction to the Developers?
Pick 1Correct
According to the Scrum definition, the Developers are self-managing and cross-functional. Therefore, the Scrum Master should continuously help the Developers to be empowered. So, the first reaction should be to ensuring if they have already tried to resolve the issue by themselves. This reaction teaches them as a self-managing Team at first they should try to resolve the problems on their own and if they could not resolve the issue then they can ask the Scrum Master for help. Furthermore, resolving issues on behalf of the Developers prevents their growth as a Team and harms their self-management. Plus, the Scrum Team as a whole should try to cope with the problems without management interference. Asking managers for help should be the last solution. Finally, the Developers should not compromise with problems, issues, and as is situations because with this approach they will not get empowered and will not be able to create high-quality valuable increments continuously.
Incorrect
According to the Scrum definition, the Developers are self-managing and cross-functional. Therefore, the Scrum Master should continuously help the Developers to be empowered. So, the first reaction should be to ensuring if they have already tried to resolve the issue by themselves. This reaction teaches them as a self-managing Team at first they should try to resolve the problems on their own and if they could not resolve the issue then they can ask the Scrum Master for help. Furthermore, resolving issues on behalf of the Developers prevents their growth as a Team and harms their self-management. Plus, the Scrum Team as a whole should try to cope with the problems without management interference. Asking managers for help should be the last solution. Finally, the Developers should not compromise with problems, issues, and as is situations because with this approach they will not get empowered and will not be able to create high-quality valuable increments continuously.
-
Question 28 of 80
28. Question
What most important things happen if the Developers decide to conduct the Daily Scrum event every three days?
Pick 3Correct
Daily Scrum is an event just for the Developers in which they check their progress towards the Sprint Goal, make a reliable plan for the next 24 hours, and raise impediments. Fundamentally, it is a great inspect and adapt opportunity. On the other hand, there are not any control mechanisms in Scrum. Therefore, managers should not control the Team. In addition, updating the Scrum board is the Developers’ responsibility. Finally, although a lot of work will be accumulated for the Team to update the Scrum board, it is not one of the most important consequences of conducting the Daily Scrum event every three days.
Incorrect
Daily Scrum is an event just for the Developers in which they check their progress towards the Sprint Goal, make a reliable plan for the next 24 hours, and raise impediments. Fundamentally, it is a great inspect and adapt opportunity. On the other hand, there are not any control mechanisms in Scrum. Therefore, managers should not control the Team. In addition, updating the Scrum board is the Developers’ responsibility. Finally, although a lot of work will be accumulated for the Team to update the Scrum board, it is not one of the most important consequences of conducting the Daily Scrum event every three days.
-
Question 29 of 80
29. Question
Who should participate in the Sprint Planning?
Pick all that applyCorrect
Participants of the Sprint Planning are all Scrum Team members i.e. the Developers, the Product Owner, and the Scrum Master. In addition, The Scrum Team may also invite other experts to provide technical or domain advice.
Incorrect
Participants of the Sprint Planning are all Scrum Team members i.e. the Developers, the Product Owner, and the Scrum Master. In addition, The Scrum Team may also invite other experts to provide technical or domain advice.
-
Question 30 of 80
30. Question
Three Teams work on the same product. You are the Scrum Master of all three Teams. One day, they come to you and explain that for a few upcoming Sprints they need an external technical expert fulltime. Over the organization, there is just one person who has this expertise. As the Scrum Master, what do you think are the most important subjects in this situation?
Pick 3Correct
In a situation that multiple Teams need a rare expert resource, at first, they should directly share the issue with that expert to collaborate with him/her for finding a solution. For example, some Developers with an interest in that expertise can be volunteers to learn from that expert and then come back to their Teams and take responsibility for that work. In addition, they should still be able to produce integrated releasable done Increments at the end of each Sprint. On the other hand, maximizing Developers’ utilization is not a goal in Scrum.
Incorrect
In a situation that multiple Teams need a rare expert resource, at first, they should directly share the issue with that expert to collaborate with him/her for finding a solution. For example, some Developers with an interest in that expertise can be volunteers to learn from that expert and then come back to their Teams and take responsibility for that work. In addition, they should still be able to produce integrated releasable done Increments at the end of each Sprint. On the other hand, maximizing Developers’ utilization is not a goal in Scrum.
-
Question 31 of 80
31. Question
Doing daily integration interrupts the Team’s focus. Therefore, they have decided to postpone all integration work into a separate Sprint called Integration Sprint. Is it acceptable behavior?
Pick 1Correct
There is just regular Sprint in Scrum within which the Developers try to create releasable Increment. Therefore, there are no such things as Sprint Zero, Hardening Sprint, Stabilization Sprint, Integration Sprint, etc.
On the other hand, if they postpone integration work to the future, they will not create a done Increment and cannot gather feedback from the market.Incorrect
There is just regular Sprint in Scrum within which the Developers try to create releasable Increment. Therefore, there are no such things as Sprint Zero, Hardening Sprint, Stabilization Sprint, Integration Sprint, etc.
On the other hand, if they postpone integration work to the future, they will not create a done Increment and cannot gather feedback from the market. -
Question 32 of 80
32. Question
A new Sprint starts immediately after the conclusion of the previous Sprint.
Pick 1Correct
There is no special time between two Sprints and new Sprint starts immediately after the conclusion of the previous Sprint.
Incorrect
There is no special time between two Sprints and new Sprint starts immediately after the conclusion of the previous Sprint.
-
Question 33 of 80
33. Question
When can a Sprint be canceled?
Pick 2Correct
A Sprint is canceled when the Sprint Goal becomes obsolete or if it no longer makes sense. This might occur if the company changes direction or because of the market or technology conditions change. Just Product Owner has the authority to cancel a Sprint. Although others can affect her, she has the final say.
Incorrect
A Sprint is canceled when the Sprint Goal becomes obsolete or if it no longer makes sense. This might occur if the company changes direction or because of the market or technology conditions change. Just Product Owner has the authority to cancel a Sprint. Although others can affect her, she has the final say.
-
Question 34 of 80
34. Question
How often should the Daily Scrum be conducted?
Pick 1Correct
Daily Scrum is a mandatory event of Scrum and is a feedback loop that the Developers synchronize their work daily and monitor progress toward the Sprint Goal. It should be conducted every working day during the Sprint.
Incorrect
Daily Scrum is a mandatory event of Scrum and is a feedback loop that the Developers synchronize their work daily and monitor progress toward the Sprint Goal. It should be conducted every working day during the Sprint.
-
Question 35 of 80
35. Question
Which one is a feedback loop?
Pick 3Correct
All four Scrum events are a type of feedback loop or inspect and adapt opportunities include Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. Although Sprint is an event, its role is being a container for other events. Product Backlog refinement is a continuous activity and is not a feedback loop.
Incorrect
All four Scrum events are a type of feedback loop or inspect and adapt opportunities include Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. Although Sprint is an event, its role is being a container for other events. Product Backlog refinement is a continuous activity and is not a feedback loop.
-
Question 36 of 80
36. Question
Additional meetings in Scrum are NOT acceptable.
Pick 1Correct
All Scrum events serve the Team to do their job efficiently and help them to have minimum extra meetings. However, if additional meetings can help them to meet the Sprint Goal better, it is an acceptable way that the Team can pursue.
Incorrect
All Scrum events serve the Team to do their job efficiently and help them to have minimum extra meetings. However, if additional meetings can help them to meet the Sprint Goal better, it is an acceptable way that the Team can pursue.
-
Question 37 of 80
37. Question
Who are the participants of the Product Backlog Refinement?
Pick 1Correct
Product Backlog Refinement is done by the Product Owner and the Developers’ collaboration. Even stakeholders could be invited to the refinement.
Incorrect
Product Backlog Refinement is done by the Product Owner and the Developers’ collaboration. Even stakeholders could be invited to the refinement.
-
Question 38 of 80
38. Question
Who creates the Definition of Done?
Pick 1Correct
If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product.
Incorrect
If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product.
-
Question 39 of 80
39. Question
What is the main purpose of the Sprint Review?
Pick 1Correct
Eliciting feedback from the stakeholders and customers is the main purpose of the Sprint Review. In addition, there is not any hand-off / sign-off in it and checking Team behavior is a topic that should be discussed in the Sprint Retrospective.
Incorrect
Eliciting feedback from the stakeholders and customers is the main purpose of the Sprint Review. In addition, there is not any hand-off / sign-off in it and checking Team behavior is a topic that should be discussed in the Sprint Retrospective.
-
Question 40 of 80
40. Question
When does the Product Owner usually share the project forecasted end date with the stakeholders?
Pick 1Correct
At any point in time, the total work remaining to reach a goal can be summed. The Product Owner could track this total work remaining at least every Sprint Review. The Product Owner compares this amount with work remaining at previous Sprint Reviews to assess progress toward completing projected work by the desired time for the goal. This information is made transparent to all stakeholders.
Incorrect
At any point in time, the total work remaining to reach a goal can be summed. The Product Owner could track this total work remaining at least every Sprint Review. The Product Owner compares this amount with work remaining at previous Sprint Reviews to assess progress toward completing projected work by the desired time for the goal. This information is made transparent to all stakeholders.
-
Question 41 of 80
41. Question
In the middle of the Sprint, the Developers find they have overcommitted. Who is responsible for adjusting the Sprint work and negotiating the scope?
Pick 1Correct
When the Developers are in the middle of the Sprint, they could not change the Sprint Backlog items by themselves. If they find they have overcommitted, they should inform the Product Owner to review the items together and negotiate the scope if necessary or they might leave the Sprint Backlog intact that may lead to some undone items at the end of the Sprint, which naturally will move back to the Product Backlog.
Incorrect
When the Developers are in the middle of the Sprint, they could not change the Sprint Backlog items by themselves. If they find they have overcommitted, they should inform the Product Owner to review the items together and negotiate the scope if necessary or they might leave the Sprint Backlog intact that may lead to some undone items at the end of the Sprint, which naturally will move back to the Product Backlog.
-
Question 42 of 80
42. Question
Which element belongs solely to the Developers?
Pick 1Correct
According to the Scrum Guide, the Sprint Backlog is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint, and it belongs solely to the Developers. The Definition of Done is created and updated by the Scrum Team.
Incorrect
According to the Scrum Guide, the Sprint Backlog is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint, and it belongs solely to the Developers. The Definition of Done is created and updated by the Scrum Team.
-
Question 43 of 80
43. Question
Which is true about the Sprint Backlog?
Pick 1Correct
The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog Items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how) and is created during the Sprint Planning. The Sprint Backlog is a plan by and for the Developers.
Incorrect
The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog Items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how) and is created during the Sprint Planning. The Sprint Backlog is a plan by and for the Developers.
-
Question 44 of 80
44. Question
In scaled Scrum environment, all the Scrum Teams should have the same Sprint length.
Pick 1Correct
In scaled Scrum, having the same Sprint length for all Scrum Teams is not mandatory. However, having the same Sprint length is a good practice. Furthermore, Scrum Teams can have different Sprint lengths and it is better that the Sprint lengths be multiple of each Sprint length. For example, if the longer Sprint is four weeks, the shorter Sprint can be two weeks while the shortest Sprint can be one week. Because at the end of the longest Sprint length, all Scrum Teams should have an opportunity to bring an integrated releasable increment collectively.
Incorrect
In scaled Scrum, having the same Sprint length for all Scrum Teams is not mandatory. However, having the same Sprint length is a good practice. Furthermore, Scrum Teams can have different Sprint lengths and it is better that the Sprint lengths be multiple of each Sprint length. For example, if the longer Sprint is four weeks, the shorter Sprint can be two weeks while the shortest Sprint can be one week. Because at the end of the longest Sprint length, all Scrum Teams should have an opportunity to bring an integrated releasable increment collectively.
-
Question 45 of 80
45. Question
Can the Developers change the Sprint Backlog?
Pick 1Correct
Sprint Backlog contains three elements: Sprint Goal, Sprint Backlog Items, and Tasks. Although changing Sprint Goal and Sprint Backlog Items are not allowed, tasks could be added or removed at any time during the Sprint when the Developers learn more about the work needed to realize the Sprint Goal. So, the Sprint Backlog could be updated and changed during the Sprint.
Incorrect
Sprint Backlog contains three elements: Sprint Goal, Sprint Backlog Items, and Tasks. Although changing Sprint Goal and Sprint Backlog Items are not allowed, tasks could be added or removed at any time during the Sprint when the Developers learn more about the work needed to realize the Sprint Goal. So, the Sprint Backlog could be updated and changed during the Sprint.
-
Question 46 of 80
46. Question
Who creates the Sprint Goal?
Pick 1Correct
The Sprint Goal is created through all Scrum Team members’ collaboration.
Incorrect
The Sprint Goal is created through all Scrum Team members’ collaboration.
-
Question 47 of 80
47. Question
What is the usual comparison of Product Backlog Items average size in the Product Backlog and Sprint Backlog?
Pick 1Correct
During the Product Backlog refinement, Items are expressed with more details and broken down to the smaller Items that can be finished in a Sprint. In addition, more effort will pay to refine Items on top of the Product Backlog because they have more probability to be implemented in the upcoming Sprints so usually PBIs on top of the Product Backlog are smaller than PBIs in the bottom. Further, the Developers select Items for the Sprint from the top of the Product Backlog. Consequently, the average size of the Items in the Product Backlog is usually larger than the size of Items in the Sprint Backlog.
Incorrect
During the Product Backlog refinement, Items are expressed with more details and broken down to the smaller Items that can be finished in a Sprint. In addition, more effort will pay to refine Items on top of the Product Backlog because they have more probability to be implemented in the upcoming Sprints so usually PBIs on top of the Product Backlog are smaller than PBIs in the bottom. Further, the Developers select Items for the Sprint from the top of the Product Backlog. Consequently, the average size of the Items in the Product Backlog is usually larger than the size of Items in the Sprint Backlog.
-
Question 48 of 80
48. Question
Who creates the Sprint Backlog?
Pick 1Correct
Creating the Sprint Backlog is a collaborative work that is done by the Scrum Team members during the Sprint Planning not before or after it.
Incorrect
Creating the Sprint Backlog is a collaborative work that is done by the Scrum Team members during the Sprint Planning not before or after it.
-
Question 49 of 80
49. Question
When is a feature done?
Pick 1Correct
Finishing Product Backlog Items is an important concept in Scrum. It emphasizes that all Team members should have a common understanding of done. Therefore, Definition of Done is introduced as part of the Scrum and defines all required work that should be completed before an end user be able to use the product and nothing else remains before its release.
Although the Product Owner approval could be required, it does not mean the PBI completeness. As a tip, the Product Owner approval would be a criteria in the Definition of Done. Furthermore, approving PBIs’ completeness is not the Scrum Master’s responsibility. In addition, there could be many things in the Definition of Done that customers do not know about such as code quality metrics’ thresholds, so customers also could not determine PBIs’ completeness. Finally, the Developers’ agreement is not enough about an Item’s completeness because they may forget to do some tasks for having a usable and releasable feature.
Done or completeness of a PBI can be explained through the following statements:
– When everything is done based on the Definition of Done
– When there is nothing more to do before it can be used by the end users
– When it is potentially releasable and shippable
– The Item is usable by the end user
Incorrect
Finishing Product Backlog Items is an important concept in Scrum. It emphasizes that all Team members should have a common understanding of done. Therefore, Definition of Done is introduced as part of the Scrum and defines all required work that should be completed before an end user be able to use the product and nothing else remains before its release.
Although the Product Owner approval could be required, it does not mean the PBI completeness. As a tip, the Product Owner approval would be a criteria in the Definition of Done. Furthermore, approving PBIs’ completeness is not the Scrum Master’s responsibility. In addition, there could be many things in the Definition of Done that customers do not know about such as code quality metrics’ thresholds, so customers also could not determine PBIs’ completeness. Finally, the Developers’ agreement is not enough about an Item’s completeness because they may forget to do some tasks for having a usable and releasable feature.
Done or completeness of a PBI can be explained through the following statements:
– When everything is done based on the Definition of Done
– When there is nothing more to do before it can be used by the end users
– When it is potentially releasable and shippable
– The Item is usable by the end user
-
Question 50 of 80
50. Question
How does the Definition of Done help the Developers?
Pick 3Correct
Definition of Done is a fundamental concept of Scrum which creates a common understanding of when work is complete, helps developers understand how many Product Backlog Items they can select for each Sprint and increases transparency. In addition, it can be considered as a development process and contains many things such as quality criteria, metrics, non-functional requirements, etc. Finally, it is created by the Scrum Team (or the organization which can make minimum rules for all teams over the organization). The Team should have a Definition of Done at least based on the organization definition or with more stringent criteria.
Incorrect
Definition of Done is a fundamental concept of Scrum which creates a common understanding of when work is complete, helps developers understand how many Product Backlog Items they can select for each Sprint and increases transparency. In addition, it can be considered as a development process and contains many things such as quality criteria, metrics, non-functional requirements, etc. Finally, it is created by the Scrum Team (or the organization which can make minimum rules for all teams over the organization). The Team should have a Definition of Done at least based on the organization definition or with more stringent criteria.
-
Question 51 of 80
51. Question
Which one is true about the Definition of Done and Acceptance Criteria?
Pick 1Correct
Definition of Done is a concept with a set of requirements that should be applied to a feature in order to be called complete. On the other hand, Acceptance Criteria or Conditions of Satisfaction contains a list of scenarios that should be passed to ensure that the feature is working as expected. The difference is that there is one Definition of Done for the product and is common for all features while there is a separate and specific Acceptance Criteria for each feature. Passing Acceptance Criteria would be an item of the Definition of Done.
Incorrect
Definition of Done is a concept with a set of requirements that should be applied to a feature in order to be called complete. On the other hand, Acceptance Criteria or Conditions of Satisfaction contains a list of scenarios that should be passed to ensure that the feature is working as expected. The difference is that there is one Definition of Done for the product and is common for all features while there is a separate and specific Acceptance Criteria for each feature. Passing Acceptance Criteria would be an item of the Definition of Done.
-
Question 52 of 80
52. Question
If a Product Backlog Item is not Ready according to the “Definition of Ready,” the Developers should not select it for the Sprint.
Pick 1Correct
There is no “Definition of Ready” concept in Scrum so the Developers cannot refuse PBIs because they are not ready. Through Product Backlog refinement, the Product Owner and the Developers collaborate to clarify all aspects of the PBIs but if they did not do so, they would select PBIs from the top of the Product Backlog, start the Sprint, and add more details to the selected PBIs during the Sprint.
Incorrect
There is no “Definition of Ready” concept in Scrum so the Developers cannot refuse PBIs because they are not ready. Through Product Backlog refinement, the Product Owner and the Developers collaborate to clarify all aspects of the PBIs but if they did not do so, they would select PBIs from the top of the Product Backlog, start the Sprint, and add more details to the selected PBIs during the Sprint.
-
Question 53 of 80
53. Question
The scaled Scrum adds or changes some parts of the Scrum framework.
Pick 1Correct
Scaled Scrum is based on the Scrum framework and uses Scrum parts as its building blocks with some additions or changes within which multiple teams work on the same product for one or more Sprints in order to produce a releasable integrated Increment at the end of each Sprint.
Scrum.org has introduced the Nexus framework for this purpose with some differences with scaled Scrum, which contains 3-9 Scrum Teams and a Nexus Integration Team.
Incorrect
Scaled Scrum is based on the Scrum framework and uses Scrum parts as its building blocks with some additions or changes within which multiple teams work on the same product for one or more Sprints in order to produce a releasable integrated Increment at the end of each Sprint.
Scrum.org has introduced the Nexus framework for this purpose with some differences with scaled Scrum, which contains 3-9 Scrum Teams and a Nexus Integration Team.
-
Question 54 of 80
54. Question
What is the Scrum of Scrums?
Pick 1Correct
When multiple teams are working on the same product, every day Developer representatives from all Teams gather to talk about new dependencies and issues that may affect other teams. This meeting is called Scrum of Scrums that is used to align all teams.
Incorrect
When multiple teams are working on the same product, every day Developer representatives from all Teams gather to talk about new dependencies and issues that may affect other teams. This meeting is called Scrum of Scrums that is used to align all teams.
-
Question 55 of 80
55. Question
How do the Teams in scaled Scrum define Definition of Done?
Pick 2Correct
When multiple Teams are working on the same product they can (not should) have one Definition of Done for all Teams or each Team can have its own one or something between these two extremes. The rule here is that their outputs should be combined and integrated continuously and at the end of the Sprint they should deliver just one integrated Increment as all Teams’ output so all Definition of Done should not violate each other.
Incorrect
When multiple Teams are working on the same product they can (not should) have one Definition of Done for all Teams or each Team can have its own one or something between these two extremes. The rule here is that their outputs should be combined and integrated continuously and at the end of the Sprint they should deliver just one integrated Increment as all Teams’ output so all Definition of Done should not violate each other.
-
Question 56 of 80
56. Question
Which factors should be considered when dividing Developers into multiple Teams in scaled Scrum?
Pick 1Correct
The Developers in Scrum are self-organizing and self-managing, so based on knowing the product and its vision, they should decide how to divide themselves into multiple teams. Moreover, nobody else such as the Product Owner, the Scrum Master, or top management should make this decision.
In addition, they should consider each team should be cross-functional which means each team should have all required skills to convert Product Backlog Items to a releasable Increment. Also, they should adhere to the recommended size of each Team.
Furthermore, based on the situations, Teams’ compositions can be changed after each Sprint if needed.
On the other hand, developers’ utilization is not important as long as the teams deliver the product to the customer continuously.
Incorrect
The Developers in Scrum are self-organizing and self-managing, so based on knowing the product and its vision, they should decide how to divide themselves into multiple teams. Moreover, nobody else such as the Product Owner, the Scrum Master, or top management should make this decision.
In addition, they should consider each team should be cross-functional which means each team should have all required skills to convert Product Backlog Items to a releasable Increment. Also, they should adhere to the recommended size of each Team.
Furthermore, based on the situations, Teams’ compositions can be changed after each Sprint if needed.
On the other hand, developers’ utilization is not important as long as the teams deliver the product to the customer continuously.
-
Question 57 of 80
57. Question
How do the Developers select PBIs in the Sprint Planning in scaled Scrum?
Pick 1Correct
All Scrum Teams’ members should be present in the Sprint Planning. The Product Owner provides domain knowledge and guides selection and priority decisions. All members discuss dependencies and their effects on each Team. Then each Team selects their PBIs with all other Teams’ consensus and Product Owner guide as their Sprint Backlog items. Each Team has a separate Sprint Backlog.
Incorrect
All Scrum Teams’ members should be present in the Sprint Planning. The Product Owner provides domain knowledge and guides selection and priority decisions. All members discuss dependencies and their effects on each Team. Then each Team selects their PBIs with all other Teams’ consensus and Product Owner guide as their Sprint Backlog items. Each Team has a separate Sprint Backlog.
-
Question 58 of 80
58. Question
How many Product Owners and Scrum Masters can be there in scaled Scrum?
Pick 2Correct
In scaled Scrum which multiple Teams work on a single Product, there is just one Product Owner, multiple Teams of Developers, and one Scrum Master position for each Team that can be filled with one or multiple Scrum Masters.
Incorrect
In scaled Scrum which multiple Teams work on a single Product, there is just one Product Owner, multiple Teams of Developers, and one Scrum Master position for each Team that can be filled with one or multiple Scrum Masters.
-
Question 59 of 80
59. Question
The best tool for comparing Teams’ performance in scaled Scrum is velocity.
Pick 1Correct
Velocity is the average amount of work that a Team can complete in a single Sprint. Its main use is helping Teams during the Sprint Planning as a guide to the Teams’ capacity. It means how much work they could pick to complete until the end of the Sprint. In addition, velocity is a relative concept, which cannot be used for comparing other projects and other Teams. Different Teams have different characteristics, skills, experiences, and different goals. Using velocity as a comparison tool is wrong that can lead Teams to focus on increasing their velocity through unacceptable ways like inflation in estimation or cutting quality corners instead of delivering high value and quality software continuously.
Incorrect
Velocity is the average amount of work that a Team can complete in a single Sprint. Its main use is helping Teams during the Sprint Planning as a guide to the Teams’ capacity. It means how much work they could pick to complete until the end of the Sprint. In addition, velocity is a relative concept, which cannot be used for comparing other projects and other Teams. Different Teams have different characteristics, skills, experiences, and different goals. Using velocity as a comparison tool is wrong that can lead Teams to focus on increasing their velocity through unacceptable ways like inflation in estimation or cutting quality corners instead of delivering high value and quality software continuously.
-
Question 60 of 80
60. Question
Postponing feature completion to the end of the release increases integration risks and related issues.
Pick 1Correct
The main purpose of the Sprint time-box is developing releasable features and getting feedback from the market, customers, and stakeholders based on done features frequently. Postponing feature completion will lead to miss gathering feedback and lose inspect and adapt opportunities and limit the Product Owner to be as nimble as possible about releasing features. In addition, each release usually contains outputs of several Sprints, and postponing feature completion to the end of the release, increases integration risks and related issues.
Incorrect
The main purpose of the Sprint time-box is developing releasable features and getting feedback from the market, customers, and stakeholders based on done features frequently. Postponing feature completion will lead to miss gathering feedback and lose inspect and adapt opportunities and limit the Product Owner to be as nimble as possible about releasing features. In addition, each release usually contains outputs of several Sprints, and postponing feature completion to the end of the release, increases integration risks and related issues.
-
Question 61 of 80
61. Question
What do a typical burn-up chart x-axis and y-axis show?
Pick 1Correct
Burn-up chart Y-axis usually shows total done work and X-axis shows a type of time i.e. Sprint days in the Sprint burn-up chart and Sprint numbers in the Project burn-up chart.
Incorrect
Burn-up chart Y-axis usually shows total done work and X-axis shows a type of time i.e. Sprint days in the Sprint burn-up chart and Sprint numbers in the Project burn-up chart.
-
Question 62 of 80
62. Question
An Increment is the sum of all selected features for the current Sprint and all previous Sprints’ done features.
Pick 1Correct
An Increment is the sum of all new done features that are added to those delivered in the previous Sprints. Each Increment can be seemed like a different version of the software and includes all previous Increments.
Incorrect
An Increment is the sum of all new done features that are added to those delivered in the previous Sprints. Each Increment can be seemed like a different version of the software and includes all previous Increments.
-
Question 63 of 80
63. Question
Who determines how work should be performed during the Sprint?
Pick 1Correct
Developers are self-managing and no one tells them how to perform work and turn the Product Backlog into Increments of potentially releasable functionalities. In addition, all Developers together as a whole are cross-functional with all required skills to create a product Increment.
Incorrect
Developers are self-managing and no one tells them how to perform work and turn the Product Backlog into Increments of potentially releasable functionalities. In addition, all Developers together as a whole are cross-functional with all required skills to create a product Increment.
-
Question 64 of 80
64. Question
Which one is NOT a sign of Commitment in Scrum Values?
Pick 1Correct
The Scrum players commit to the team. Commit to quality. Commit to collaborate. Commit to learn. Commit to do the best they can, every day again. Commit to the Product Goal. Commit to the Sprint Goal. Commit to act as professionals. Commit to self-management. Commit to self-organization. Commit to excellence. Commit to the Agile values and principles. Commit to create working versions of product. Commit to look for improvements. Commit to the Definition of Done. Commit to the Scrum framework. Commit to focus on value. Commit to finish work. Commit to inspect and adapt. Commit to transparency. Commit to challenge the status-quo.
On the other hand, the Team in the Sprint Planning works to forecast (not commit) the functionality that will be developed during the Sprint.Incorrect
The Scrum players commit to the team. Commit to quality. Commit to collaborate. Commit to learn. Commit to do the best they can, every day again. Commit to the Product Goal. Commit to the Sprint Goal. Commit to act as professionals. Commit to self-management. Commit to self-organization. Commit to excellence. Commit to the Agile values and principles. Commit to create working versions of product. Commit to look for improvements. Commit to the Definition of Done. Commit to the Scrum framework. Commit to focus on value. Commit to finish work. Commit to inspect and adapt. Commit to transparency. Commit to challenge the status-quo.
On the other hand, the Team in the Sprint Planning works to forecast (not commit) the functionality that will be developed during the Sprint. -
Question 65 of 80
65. Question
Who should know the most about the progress toward a business objective or a release?
Pick 1Correct
The Product Owner is the representative of the customer and market and maximizes the value of the Product, which is developed with the Developers. Therefore, she/he should know the most about the progress toward a business objective or a release.
Incorrect
The Product Owner is the representative of the customer and market and maximizes the value of the Product, which is developed with the Developers. Therefore, she/he should know the most about the progress toward a business objective or a release.
-
Question 66 of 80
66. Question
When an Increment is born?
Pick 1Correct
The moment a Product Backlog item meets the Definition of Done, an Increment is born. The Product Owner acceptance or finishing all tests do not mean meeting the Definition of Done, although they can be part of the Definition of Done. On the other hand, completing all tasks of the Product Backlog Item does not mean it works and is usable because the Developers might have not determined all required tasks to have a usable PBI.
Incorrect
The moment a Product Backlog item meets the Definition of Done, an Increment is born. The Product Owner acceptance or finishing all tests do not mean meeting the Definition of Done, although they can be part of the Definition of Done. On the other hand, completing all tasks of the Product Backlog Item does not mean it works and is usable because the Developers might have not determined all required tasks to have a usable PBI.
-
Question 67 of 80
67. Question
Which two of the following options are true?
Pick 2Correct
Developers should have some guidelines for deciding and handling architectural and infrastructural concerns. They should handle these concerns as a part of other Product Backlog Items during each Sprint. Doing a lot upfront in order to make a comprehensive architecture at the beginning of the project is a type of waste. Handling architecture should be done incrementally based on the learnings that emerge during the Sprints. It is obvious that it uses more effort at the early Sprints and decreases during the middle and last Sprints. On the other hand, during each Sprint, the Team should try to produce at least one potential releasable business functionality in order to get feedback from customers. Therefore, adding architectural and infrastructural items to the Product Backlog in order to do in the early Sprints is a valid policy.
In addition, there is no title and no sub-team among the Developers. Therefore, having an Architect role or architecture sub-team is not acceptable.
Incorrect
Developers should have some guidelines for deciding and handling architectural and infrastructural concerns. They should handle these concerns as a part of other Product Backlog Items during each Sprint. Doing a lot upfront in order to make a comprehensive architecture at the beginning of the project is a type of waste. Handling architecture should be done incrementally based on the learnings that emerge during the Sprints. It is obvious that it uses more effort at the early Sprints and decreases during the middle and last Sprints. On the other hand, during each Sprint, the Team should try to produce at least one potential releasable business functionality in order to get feedback from customers. Therefore, adding architectural and infrastructural items to the Product Backlog in order to do in the early Sprints is a valid policy.
In addition, there is no title and no sub-team among the Developers. Therefore, having an Architect role or architecture sub-team is not acceptable.
-
Question 68 of 80
68. Question
Can a feature with small bugs be considered as a done deliverable?
Pick 1Correct
No. having a feature with small bugs means it is not releasable so the Product Owner cannot accept it as a deliverable.
Incorrect
No. having a feature with small bugs means it is not releasable so the Product Owner cannot accept it as a deliverable.
-
Question 69 of 80
69. Question
Which is true about the required effort amount for preparing development environment, tools, and infrastructures in a project lifecycle?
Pick 1Correct
The development environment, tools, and infrastructures required for the development should be prepared and improved gradually during the project. It is obvious that it uses more effort at early Sprints and decreases during the middle and last Sprints. In addition, during each Sprint, the Team should try to produce at least one potential releasable business functionality in order to get feedback from customers.
Incorrect
The development environment, tools, and infrastructures required for the development should be prepared and improved gradually during the project. It is obvious that it uses more effort at early Sprints and decreases during the middle and last Sprints. In addition, during each Sprint, the Team should try to produce at least one potential releasable business functionality in order to get feedback from customers.
-
Question 70 of 80
70. Question
How can the Scrum Team manage non‐functional requirements in Scrum?
Pick 2Correct
The non-functional requirements or cross-cutting concerns are the features of the design that may apply across all layers and are related to the quality requirements. There are many non-functional requirements as following: Security, Reliability, Performance, Availability, Globalization, Scalability, Maintainability, Robustness, etc. They can be managed by adding them to the Definition of Done, the Product Backlog, or acceptance criteria.
Incorrect
The non-functional requirements or cross-cutting concerns are the features of the design that may apply across all layers and are related to the quality requirements. There are many non-functional requirements as following: Security, Reliability, Performance, Availability, Globalization, Scalability, Maintainability, Robustness, etc. They can be managed by adding them to the Definition of Done, the Product Backlog, or acceptance criteria.
-
Question 71 of 80
71. Question
What is NOT true about technical debt?
Pick 1Correct
Technical debt comes from making bad technical decisions and is the eventual consequence of poor technical choices. The Team should pay it back continuously. If the Team does not pay back, it will decrease the development speed over time. Although its measurement is hard, its growth would lead to wrong assumptions about Increments delivery and even might prevent creating the releasable product.
On the other hand, each Sprint’s purpose is to create at least one releasable business functionality. So stopping it to pay the technical debt back is not a proper policy.
Incorrect
Technical debt comes from making bad technical decisions and is the eventual consequence of poor technical choices. The Team should pay it back continuously. If the Team does not pay back, it will decrease the development speed over time. Although its measurement is hard, its growth would lead to wrong assumptions about Increments delivery and even might prevent creating the releasable product.
On the other hand, each Sprint’s purpose is to create at least one releasable business functionality. So stopping it to pay the technical debt back is not a proper policy.
-
Question 72 of 80
72. Question
Which one can be done in the Sprint Retrospective?
Pick 3Correct
The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done. In addition, The Sprint Retrospective concludes the Sprint. The most impactful improvements are addressed as soon as possible not necessarily in the next Sprint.
In addition, the Scrum Team plans ways to increase product quality by improving work processes or adapting the Definition of Done.Incorrect
The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done. In addition, The Sprint Retrospective concludes the Sprint. The most impactful improvements are addressed as soon as possible not necessarily in the next Sprint.
In addition, the Scrum Team plans ways to increase product quality by improving work processes or adapting the Definition of Done. -
Question 73 of 80
73. Question
There can be a special situation that the Developers update the Product Backlog.
Pick 1Correct
The Product Owner owns the Product Backlog and is the sole person for its management. However, Product Backlog Items can be updated at any time by the Product Owner or at the Product Owner’s discretion. In such a situation, the Product Owner can delegate some of his/her responsibilities to others but accountability remains for him/her.
Incorrect
The Product Owner owns the Product Backlog and is the sole person for its management. However, Product Backlog Items can be updated at any time by the Product Owner or at the Product Owner’s discretion. In such a situation, the Product Owner can delegate some of his/her responsibilities to others but accountability remains for him/her.
-
Question 74 of 80
74. Question
The most important identified improvement in the last Sprint Retrospective can be an input to the Sprint Planning.
Pick 1Correct
Inputs to the Sprint Planning are the last Increment, capacity of the Developers for current Sprint, Team’s last velocity or performance, the Product Backlog, the Definition of Done, and even a list of improvements resulted in the past Sprint Retrospectives.
Incorrect
Inputs to the Sprint Planning are the last Increment, capacity of the Developers for current Sprint, Team’s last velocity or performance, the Product Backlog, the Definition of Done, and even a list of improvements resulted in the past Sprint Retrospectives.
-
Question 75 of 80
75. Question
According to the Scrum Guide 2020, Scrum is:
Pick 1Correct
According to the Scrum Guide 2020, Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems.
Incorrect
According to the Scrum Guide 2020, Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems.
-
Question 76 of 80
76. Question
Which one is NOT a required tool for the Scrum Master to do his/her responsibilities?
Pick 1Correct
There are many tools for the Scrum Master to do his/her responsibilities including coaching, mentoring, teaching, facilitating, servant leadership, convincing, and managing the Scrum process.
On the other hand, there is no authority for the Scrum Master to command people and fundamentally, there are not any types of control outside the Team in Scrum.Incorrect
There are many tools for the Scrum Master to do his/her responsibilities including coaching, mentoring, teaching, facilitating, servant leadership, convincing, and managing the Scrum process.
On the other hand, there is no authority for the Scrum Master to command people and fundamentally, there are not any types of control outside the Team in Scrum. -
Question 77 of 80
77. Question
How often do the Scrum Team members inspect their work?
Pick 1Correct
Scrum users must frequently inspect Scrum Artifacts and progress toward the Sprint Goal to detect undesirable variances. Their inspection should not be so frequent that inspection gets in the way of the work. Inspections are most beneficial when diligently performed by skilled inspectors at the point of work.
Incorrect
Scrum users must frequently inspect Scrum Artifacts and progress toward the Sprint Goal to detect undesirable variances. Their inspection should not be so frequent that inspection gets in the way of the work. Inspections are most beneficial when diligently performed by skilled inspectors at the point of work.
-
Question 78 of 80
78. Question
If one Scrum Team member finds an unacceptable deviation when should the Team respond to it?
Pick 1Correct
Scrum is fundamentally based on the empirical process control theory which is upheld by three pillars i.e. transparency, inspection, and adaptation. In addition, Scrum uses an adaptive approach to minimize deviation effects. Therefore, if one Scrum Team member finds an unacceptable deviation, the Team should respond to it as soon as possible to prevent further deviation.
Incorrect
Scrum is fundamentally based on the empirical process control theory which is upheld by three pillars i.e. transparency, inspection, and adaptation. In addition, Scrum uses an adaptive approach to minimize deviation effects. Therefore, if one Scrum Team member finds an unacceptable deviation, the Team should respond to it as soon as possible to prevent further deviation.
-
Question 79 of 80
79. Question
The Scrum Team may also invite other people to attend to the Sprint Planning to provide technical or domain advice.
Pick 1Correct
According to the Scrum Guide, for the Sprint Planning, the Scrum Team may also invite other people to attend to provide technical or domain advice.
Incorrect
According to the Scrum Guide, for the Sprint Planning, the Scrum Team may also invite other people to attend to provide technical or domain advice.
-
Question 80 of 80
80. Question
Which is acceptable during the Sprint?
Pick all that applyCorrect
During the Sprint, no changes that endanger the Sprint Goal are acceptable, but the Developers can negotiate the work scope with the Product Owner. They also have an expected quality based on the Definition of Done that should adhere to.
Incorrect
During the Sprint, no changes that endanger the Sprint Goal are acceptable, but the Developers can negotiate the work scope with the Product Owner. They also have an expected quality based on the Definition of Done that should adhere to.